HR 301 · 119th Congress

GEO Act

geothermal energypermitting reformpublic landsenergy development
Share

Last action 2026-05-20

Sponsored by Rep. Maloy, Celeste [R-UT-2] (R) — UT

Click any stage to learn more about the legislative process.

Would require the Department of the Interior to approve or deny geothermal drilling permit applications within 60 days of completing all required environmental reviews, even if a related lawsuit is pending — unless a federal court has vacated the underlying lease or issued injunctive relief.

The bill targets a specific bottleneck in geothermal project development: permitting delays that can stretch indefinitely while litigation over related leases works through the courts, even after agencies have finished their environmental reviews.

What this bill would do

What it would do

The bill would amend Section 4 of the Geothermal Steam Act of 1970 to impose a 60-day processing deadline on the Secretary of the Interior for applications related to geothermal drilling permits, sundry notices, notices to proceed, rights-of-way, and any other authorization under a valid existing geothermal lease. The clock would start only after all required federal reviews are complete — including reviews under the National Environmental Policy Act, the Endangered Species Act, and the National Historic Preservation Act. Critically, the deadline would apply even if a civil lawsuit affecting the application is pending, unless a federal court has specifically vacated the underlying lease or issued injunctive relief against it.

The bill would not grant federal courts any new authority and explicitly preserves existing judicial review of geothermal leases and permits. It applies only to authorizations under valid existing leases, not to the initial leasing process. No new environmental exemptions are created; all current review requirements remain in place before the 60-day window begins.

Key provisions

  1. 1Would require the Secretary of the Interior to approve or deny geothermal drilling permit applications and related authorizations within 60 days of completing all required federal environmental and regulatory reviews.Sec. 2
  2. 2Would provide that the 60-day deadline applies even if a pending civil lawsuit affects the application, unless a federal court has vacated the underlying lease or issued injunctive relief.Sec. 2
  3. 3Would explicitly preserve existing federal court authority to vacate or issue injunctive relief for geothermal leases and authorizations — no new judicial powers are granted or removed.Sec. 2
  4. 4Would define 'authorization' broadly to include any federal license, permit, approval, finding, determination, or interagency consultation required to site, construct, or begin operations of a geothermal project.Sec. 2

Who would be affected

Geothermal energy developers holding valid existing federal leases who are awaiting drilling permits or other project authorizations from the Interior Department. Federal agencies — primarily Interior — that review and issue those permits. Environmental and historic-preservation review bodies whose completed findings would trigger the 60-day clock. Communities and environments near proposed geothermal sites remain subject to existing NEPA and ESA protections before the clock starts.

Why it matters

Developers have faced extended permit limbo when litigation over a related lease proceeds slowly through courts, even after all environmental reviews are finished. A binding 60-day post-review deadline would reduce that uncertainty, potentially accelerating geothermal project development on existing federal leases. The narrow court-ordered suspension carve-out means the deadline can be paused only by an actual judicial order — not merely the filing of a lawsuit.

What would change

Changes to existing law

Amends Geothermal Steam Act of 1970 (30 U.S.C. 1003) (Sec. 2)

Adds a new subsection requiring Interior to act on geothermal permit applications within 60 days of completing all required federal reviews, notwithstanding pending civil actions.

Agencies directed to act

Department of the Interior

How implementation would work

The Secretary of the Interior would need to track the completion date of all required federal reviews for each pending geothermal application and then issue an approval or denial within 60 days of that date. No new rulemaking is explicitly required, but Interior would need to monitor active litigation on each underlying lease to determine whether a court order suspends the deadline. The bill contains no reporting requirements, grant mechanisms, or phase-in schedules. Enforcement would likely run through existing administrative and judicial review channels for agency inaction.

Legislative status & sources

Latest action

Placed on the Union Calendar, Calendar No. 568.

2026-05-20

Official CRS summary

Show the CRS summary

This bill expands the Geothermal Steam Act of 1970 to establish a deadline for the Department of the Interior to process applications related to geothermal leases. Specifically, Interior must process each application for a geothermal drilling permit or other authorization under a valid existing geothermal lease within 60 days after completing all requirements under applicable federal laws and regulations (including the National Environmental Policy Act of 1969, the Endangered Species Act of 1973, and the National Historic Preservation Act) unless a U.S. federal court vacates or provides injunctive relief for the underlying lease.

From the Congressional Research Service.

Legislative subjects

Alternative and renewable resources; Electric power generation and transmission; Energy; Licensing and registrations; Mining; Performance measurement

Committee report

H. Rept. 119-654

Congressional Bill

Ask GovernmentReporter about this bill

Ask anything about this bill. The AI can look up referenced laws and statutes to provide context.

HR 301: GEO Act | Legislation Reporter